I watched a tutorial about SDL & Kroger PI.  Is there a similar way to "top off" items for McLane via a spreadsheet?  From what I understand, each item that needs to be completed is done one at a time.  

1 Solution

Accepted Solutions

kxsRSC
Contributor

Hi - I did find the link on the training helpful but it really doesn't point out the the product mass update very well but I was able to find it under "select action".  I have shared this info with a co-worker that performs this function in PI to try it out.  I will reach out if more assistance is needed but for now, I will accept this as a solution.

View solution in original post

3 Replies

alien
Community Support

Hello @kxsRSC  and thanks for continuing the use of the community.

Unfortunately, there is no option to use a SDL spreadsheet to make those updates. Mclane only requires 5 attributes to to be topped off in product introduction. You can select multiple items and select the product mass update if you wish to add the same data on multiple items but I do not see the option to export the items into a spreadsheet and use it to mass update items. You can confirm that by looking at the documentation we have for McLane: https://community.1worldsync.com/t5/McLane-Training/ct-p/McLaneTraining 

If you have any further questions please let me know. Thank you and have a great day.

kxsRSC
Contributor

Hi - I did find the link on the training helpful but it really doesn't point out the the product mass update very well but I was able to find it under "select action".  I have shared this info with a co-worker that performs this function in PI to try it out.  I will reach out if more assistance is needed but for now, I will accept this as a solution.

Hello @kxsRSC and thanks for the feedback. Please do let us know if you or your co-worker have any follow-up questions.